That was enough for our framer Danny to begin so he was out there yesterday morning at 7:00 am. Some lumber was delivered by 8:00 but the city hadn't yet connected the temporary electric. Danny had a small generator to power just a saw so he went to cutting but I didn't know how long before the city utilities would show up so I borrowed a friends' generator and took it out for Danny to use. With it he was able to run his air compressor for his nail guns.
As it turned out I'm glad I did that becuase the City didn't connect
the power until 2:00. With the generators Danny was able to just
about complete the basement framing and get ready for putting the
I-joists on today. Very exciting to see some real construction.