Work resumed this week with gravel backfill against the foundation walls and the footing for the garage and front porch poured. We'll next have the short foundation walls for the garage and porch done and then the garage and basement floors poured. There are a lot of steps to having a concrete foundation and basement.
Our framer, Danny, will start soon after enough concrete work is done, hopefully sometime next week. I'll be getting the temporary electrical pole put in and accessible soon also. Today after work I'll be out cutting up more of the four oak trees that were pushed down.